Permits for dormering
For those of you who dormered or did exterior renovations/additions, how long did it take for your permits/plans to be approved from the time they were submitted? TIA
|
Posted 7/24/09 6:32 PM |
| |
|
Prudential Douglas Elliman Real Estate
Long Island's Largest Bridal Resource | Long Island Weddings |
CurlyQ

Member since 6/07 2024 total posts
Name:
|
Re: Permits for dormering
Which town? Town of Oyster Bay took over 3 months for the building permit and from what I have heard, that was quick.
|
Posted 7/24/09 6:41 PM |
| |
|
Rycois
Blessed with 2blue/2pink

Member since 12/05 13341 total posts
Name: J
|
Re: Permits for dormering
Town of Hempstead
|
Posted 7/24/09 6:54 PM |
| |
|
KLSbear
LIF Adult
Member since 1/06 1908 total posts
Name: Karen
|
Re: Permits for dormering
Ours took about a 4 - 6 weeks in the town of Islip. Submitted them with plans, returned for revisions in about 10 days, about 2 weeks for the revisions and we had the permit shortly after. I think we submitted it in late Sept. or early Oct. and we had the permits mid November.
|
Posted 7/24/09 8:58 PM |
| |
|
FranB
LIF Adolescent
Member since 9/06 686 total posts
Name: Fran
|
Re: Permits for dormering
Hempstead is running 4 - 6 weeks right now...
|
Posted 7/24/09 10:39 PM |
| |
|
ave1024
I Took The Wrong Road

Member since 12/07 6153 total posts
Name: That Led To The Wrong Tendencies
|
Re: Permits for dormering
About 4 weeks with Town of Hempstead for my side extension.
I am adding a Portico and I think they are moving even quicker now.
However a full dormer's plans may be looked at more closely and could take longer.
|
Posted 7/25/09 2:29 AM |
| |
|
GoldenRod
10 years on LIF!

Member since 11/06 26792 total posts
Name: Shawn
|
Re: Permits for dormering
Town of Islip... 5 days..... past the first year... Yup, 370 days, but we needed two variances because someone missed the 2nd variance issues the first time around....
|
Posted 7/25/09 7:23 PM |
| |
|
Rycois
Blessed with 2blue/2pink

Member since 12/05 13341 total posts
Name: J
|
Re: Permits for dormering
Posted by FranB
Hempstead is running 4 - 6 weeks right now...
This would be great ! We were told 8 wks by the contractor so anything sooner would be great.
|
Posted 7/26/09 1:42 PM |
| |
|
FranB
LIF Adolescent
Member since 9/06 686 total posts
Name: Fran
|
Re: Permits for dormering
I filed a permit for an extension on 6/25/09. Its already approved and it was slightly delayed for a missing form. If everything goes smoothly, you should have your permit in 4-6 weeks for sure...
|
Posted 7/26/09 2:08 PM |
| |
|
Rycois
Blessed with 2blue/2pink

Member since 12/05 13341 total posts
Name: J
|
Re: Permits for dormering
Bumping, any other experiences?
|
Posted 7/28/09 1:06 PM |
| |
|