Re: How long does it take to obtain a CO?
Posted 11/30/2007 12:07:25 PM by csorisi In the case I am speaking of the company who built the sunroom started the permit process and completed the process to get the c/o once we bugged them but it really depends on the contractor and who they used. IF they used a company it is possible they did the work if they used a handyman he may not of. In the town in this case they needed an electical certificate a fire underwriters and architecture evaluation and a survey. Once the town had these items they then had to do a final inspection. Even though your paperwork might all be in it might take the town a long time to do the inspection depending on how many people are before you. Also it might be a longer process if a permit wasn't even filed. |